On 18 November 2026, the Council announced a provisional agreement with the European Parliament on the directive to accelerate permit-granting for renewable energy, electricity grids, storage and recharging stations. It is the first of the two legislative files in the European Grids Package, which the Commission presented on 10 December 2025. The second, a revision of the TEN-E Regulation on cross-border energy infrastructure, is heading for a final round of negotiations in early December. Once the directive is adopted, Member States will have 18 months to transpose it. The deal matters to energy developers, but also to any company that needs a grid connection to electrify its processes, install batteries or charging points, or invest in on-site solar.
In short
- Fixed deadlines. According to Parliament, permits for solar installations with co-located storage (excluding hydrogen) must be granted within three months, for stand-alone storage and recharging stations within six months, and for pumped hydro storage within two years.
- Faster grid connections. Grid connection deadlines will be three months, extendable to six if duly justified.
- Fewer permits for small installations. The threshold above which permits are required rises from 100 kW to 200 kW for small solar, storage (excluding hydrogen) and recharging installations; recharging stations of up to 1 MW on artificial structures need no administrative permit.
- Overriding public interest. Renewable and grid projects are presumed to be of overriding public interest; Member States may set this aside only in duly justified cases involving cultural heritage or security and defence.
- Not yet in force. Parliament and Council still have to endorse the text, and Member States must transpose it — in Belgium at federal and regional level. In the TEN-E file, cross-border planning and congestion income are still open.
Why permitting is the bottleneck
According to Parliament, an electricity transmission grid takes about ten years to complete, with permitting accounting for more than half of that time. Permitting for renewable energy can take up to nine years, depending on the Member State and the technology, and for storage between one and seven years.
The 2023 revision of the Renewable Energy Directive (Directive (EU) 2023/2413, ‘RED III’) already introduced permitting deadlines, a presumption of overriding public interest and ‘renewables acceleration areas’, which Member States had to designate by February 2026. The new directive (COM(2025) 1007, procedure 2025/0400(COD)) amends RED III, the Electricity Directive (EU) 2019/944 and the Gas and Hydrogen Directive (EU) 2024/1788, and extends that approach to grids, storage and recharging stations. It also changes the authorisation procedure for gas and hydrogen infrastructure (Article 8 of that directive); this analysis focuses on electricity and renewables. For industrial manufacturing projects, the proposed Industrial Accelerator Act takes a similar approach.
What the Commission proposed
The Commission’s proposal of 10 December 2025, as summarised by Parliament’s research service, would:
- set a time limit of two years, extendable by one year, for authorising transmission and distribution grid projects (amended Article 8 of the Electricity Directive), and require digital platforms for permit applications;
- cap permitting at three months for solar installations above 100 kW on artificial structures, including co-located storage (Articles 16b and 16d RED), and at six months for stand-alone storage (other than hydrogen) and recharging stations above 100 kW; installations of 100 kW or less would need no administrative permit;
- set deadlines for grid connection permits: one month below 100 kW, three months for solar and co-located storage above 100 kW;
- deem procedural steps approved if the authority misses its deadline (‘tacit approval’), except for environmental decisions and grid connection permits (Article 16b RED);
- presume renewables, their grid connections, grids, storage and recharging stations to be of overriding public interest (Article 16f RED), for grids on a temporary basis;
- require projects above 10 MW to share benefits with local communities, and a single digital portal for all permitting steps.
What was agreed
Parliament adopted its negotiating mandate in July 2026 (rapporteur Niels Fuglsang, S&D, Denmark); the Council agreed its position on 26 June 2026. The Council’s text made tacit approval optional and limited it to intermediate steps, made digital portals optional and allowed two years for transposition. Parliament wanted shorter grid deadlines — one year for distribution, two for transmission — and wider use of tacit approval.
According to Parliament’s press release, the provisional agreement compares with the proposal as follows:
| Commission proposal (December 2025) | Provisional agreement (November 2026) | |
|---|---|---|
| Solar with co-located storage (excluding hydrogen) | 3 months (above 100 kW, on artificial structures) | 3 months |
| Stand-alone storage, recharging stations | 6 months (above 100 kW) | 6 months; pumped hydro storage 2 years |
| Grid connection | 1 month below 100 kW; 3 months for solar and storage above 100 kW | 3 months, extendable to 6 if duly justified; derogation for isolated and small connected systems, such as in the outermost regions |
| No administrative permit needed | 100 kW or less (solar, storage, recharging) | Up to 200 kW (storage excluding hydrogen); recharging stations up to 1 MW on artificial structures |
| Benefit sharing | Projects above 10 MW | Projects from 7 MW; renewable energy communities exempt |
| Overriding public interest | Presumption for renewables, grids, storage, recharging | Presumption; exceptions only for cultural heritage or security and defence, if duly justified |
The agreement also gives each Member State a single digital portal for all permitting steps and creates a dedicated EU-wide permitting framework for electricity grid infrastructure. According to Renew Europe, Member States will have to map and designate enough acceleration areas before they can rule out land for renewables, and countries with existing national benefit-sharing schemes face no additional requirements. Member States may use benefit sharing to support vulnerable customers and people affected by energy poverty.
The press releases do not yet give the final deadlines for grid projects or the final scope of tacit approval. Both will be clear once the compromise text is published.
Where the file stands (18 November 2026)
- Permitting directive. The Irish Presidency was due to debrief Member States’ ambassadors (Coreper) on the outcome on 18 November. Parliament’s industry committee (ITRE) votes on the text at a forthcoming meeting, followed by the plenary and formal adoption by the Council, after legal-linguistic revision. The directive enters into force twenty days after publication in the Official Journal; the 18-month transposition period runs from then.
- TEN-E Regulation. The revision (COM(2025) 1006, procedure 2025/0399(COD)) would introduce EU-wide planning of cross-border infrastructure around a central scenario, require transmission system operators to reserve part of their congestion income for projects on the Union list, and make cross-border cost sharing more predictable. The Commission has also identified eight ‘energy highways’, priority projects to remove key bottlenecks. The Council agreed its position on 26 June; Parliament’s mandate (rapporteur Tsvetelina Penkova, S&D) was confirmed in September.
- Still open in TEN-E. At a third trilogue on 10 November, the negotiators made progress on central planning and congestion income but settled neither, according to Agence Europe. The Council wants the central scenario adopted by implementing act, with Member States verifying data and assumptions; Parliament broadly backs the Commission’s central planning. On congestion income, the Council wants a phase-in from 10% rising by five percentage points a year to 25%; Parliament wants 30%. The negotiators expect a final trilogue in early December.
What it means in Belgium
- Several legislators, one deadline. Renewable energy (except federal offshore wind), distribution and local transmission up to 70 kV are regional matters, with their own regulators (VREG, CWaPE, Brugel). The transmission grid and offshore wind are federal, regulated by the CREG. Transposition will therefore require federal and regional legislation within the same 18 months.
- Different starting points. Wallonia partially transposed RED III with its decree of 29 April 2024 on accelerating renewable energy: regional mapping, acceleration zones designated by plan, a presumption of overriding public interest under its water and nature conservation rules, and lighter rules for solar installations up to 15 kW. Flanders implements RED III, the Critical Raw Materials Act and the Net-Zero Industry Act through its environmental permit legislation; the amending decree, which provides for a presumption of overriding public interest and a central contact point, went to the Flemish Parliament’s final vote on 4 March 2026. Both frameworks will have to be checked against the new thresholds, deadlines and portal requirement.
- Connection capacity remains the constraint. In March 2026, according to Fluvius data cited by Voka, about 1,250 projects in Flanders could not be connected to the grid in the usual way, around 600 of them battery parks. A three-month deadline for the connection procedure strengthens an applicant’s position, but it does not create grid capacity.
- Grid projects. The Ventilus high-voltage line, 82 km from Zeebrugge to Avelgem, shows the timescales: the regional spatial plan was approved in 2023 and the environmental permits in April 2026. On 13 November 2026, the Flemish government announced that the Council of State had rejected requests to annul the spatial plan; appeals against the permits are still pending. The new EU framework for grid permitting will shape the legal setting for the next projects of this kind.
What to do now
- Check which regime applies to your projects. Companies planning rooftop solar, batteries or charging hubs should check whether their installations fall below the new 200 kW threshold, or the 1 MW threshold for recharging stations on artificial structures, and which deadlines apply above it.
- Plan connections for capacity, not only for deadlines. Faster procedures will help, but in congested areas a connection still depends on grid reinforcement and on what the grid operator can offer, including flexible connections. Build that into investment timelines.
- Follow transposition at both levels. Several choices are left to Member States, including the design of the digital portal and of benefit-sharing schemes. In Belgium, that means the federal government and three regions, each with its own timetable.
- Prepare for benefit sharing. Developers of wind and solar projects from 7 MW should prepare a benefit-sharing model for local communities and check whether a regional scheme already exists.
- Weigh in on TEN-E before December. Congestion income and central planning affect interconnector investment, network tariffs and the selection of cross-border projects, including hydrogen. The final trilogue is expected in early December.
Sources
- European Parliament, Electricity grids: MEPs reach deal with Council on faster project permitting, press release, 18 November 2026.
- Council of the EU, Grids package: Council and Parliament agree to streamline permitting for a faster clean energy transition, press release, 18 November 2026; Reuters, EU reaches provisional deal to speed permits for renewable energy projects, 18 November 2026 (republished by bdnews24), and Anadolu Agency, EU reaches provisional deal to fast-track permits for renewable energy projects, electricity grids, 18 November 2026 (the latter two reporting the Council’s announcement).
- Renew Europe, Renew Europe welcomes agreement on faster grid permitting, 18 November 2026.
- Council of the EU, Provisional agenda of Coreper I, 18 and 20 November 2026, ST 15727/1/26 REV 1, 16 November 2026.
- European Commission, European grids package, DG Energy, and Enabling framework for renewables.
- European Parliamentary Research Service, Acceleration of permit-granting procedures, briefing, January 2026.
- European Parliament, Legislative Observatory, procedures 2025/0400(COD) and 2025/0399(COD).
- Council of the EU, General approach on the acceleration of permit-granting procedures, ST 10740/26 and general approach on the TEN-E Regulation, ST 10746/26, 23 June 2026; Transport, Telecommunications and Energy Council (Energy), 26 June 2026.
- European Parliamentary Research Service, Guidelines for trans-European energy infrastructure: revision of the TEN-E Regulation, 26 January 2026.
- Euronews, Parliament pushes tougher energy permit deadlines, setting up clash with EU countries, 14 September 2026.
- Agence Europe, ‘Networks’ package/TEN-E Regulation: most politically sensitive aspects deferred to final round, 15 October 2026, and TEN-E Regulation: Council and Parliament make progress on central scenario and congestion income and expect agreement in early December, 12 November 2026 (paywall).
- Clean Air Task Force, A step closer to a genuine energy union in the EU, September 2026.
- Elia, Legal framework: Belgium.
- Walloon Region, Décret du 29 avril 2024 relatif à l’accélération du déploiement des énergies renouvelables, Moniteur belge 13 September 2024.
- Minaraad, Briefadvies 25-014 on the draft decree implementing RED III, CRMA and NZIA, 10 June 2025; Flemish Government, final approval of the draft decree, 28 November 2025; Flemish Parliament, plenary agenda of 4 March 2026 (document 604 (2025-2026)).
- Solar Magazine, Vol stroomnet weegt op Vlaamse investeringen, 29 October 2026 (citing Voka and Fluvius).
- Belga News Agency, Flemish environment minister grants planning permission for controversial Ventilus power line project, 27 April 2026, and Belga via DH, Projet Ventilus: le Conseil d’État rejette les requêtes en annulation, 13 November 2026.
This analysis reflects the state of the file on 18 November 2026. We update it when the file moves.